Project Goal and Scope: The goal is to improve the overall Campus Electrical Capacity and Infrastructure. Segregation and relocation of branch circuits to their appropriate branch. Installing necessary security branch(s). Addressing issues associated with: voltage drop, short circuit, coordination or compliance with other electrical codes. Draft Schedule:Procurement Start – Q3 / Q4 2024Board Award Professional Services - Q4 2024Design Phase Start - Q1 2025Board Award Construction – Q1 / Q2 2026Construction NTP - Q2 2026Substantial Completion – Q3 2027ROM Construction Cost: $20-25M